A farmer is building a fence on his land. What is the expected completion time of the project? Optimistic Most Likely Pessimistic Activi orner Posts
A farmer is building a fence on his land. What is the expected completion time of the project?
Optimistic Most Likely Pessimistic Activi orner Posts trin Line Holes t Posts eldT Bar a int ack Wire time 7 10 11 9 time 8 12 14 11 11 12 time 9 14 17 14 13 16 Predecessor orner Posts trin Line trin Line Holes, Plant Posts eldT Bar