A firm is using Kanban system. The daily demand is 1,500 units and each container has a wait time of 0.04/day, and a processing time
A firm is using Kanban system. The daily demand is 1,500 units and each container has a wait time of 0.04/day, and a processing time of 0.16 days. The Container size is 60 units and the safety factor () is 12%. (Note that lead-time is the summation of waiting time and processing time.). The number of containers required is ____.