A firm uses machine hours to allocate overhead cost. During the period, budgeted variable overhead is Rs. 10000 and budgeted machine hours is 100 hours
A firm uses machine hours to allocate overhead cost. During the period, budgeted variable overhead is Rs. 10000 and budgeted machine hours is 100 hours for budgeted volume of 1000 units. The firm produced 1200 units consuming 150 hours and spent Rs. 15000 towards variable overhead. The total variable overhead cost variance is
A. Rs. 3000 favorable
B. Rs. 5000 favorable
C. Rs. 5000 adverse
D. Rs. 3000 adverse