Question
A firm wishes to bid on a contract that is expected to yield the following after-tax net cash flows at the end of each year:
A firm wishes to bid on a contract that is expected to yield the following after-tax net cash flows at the end of each year:
Year | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Net Cash Flow | 5000 | 8000 | 9000 | 8000 | 8000 | 5000 | 3000 | -1500 |
To secure the contract, the firm must spend $30,000 to retool its plant. This retooling will have no salvage value at the end of the 8 years. Comparable investment alternatives are available to the firm that earns 12 percent compounded annually. The depreciation tax benefit from the retooling is reflected in the net cash flows in the table. Compute the project's net present value. Should the project be adopted?(155.8 Yes)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started