Question
A fixed price contract including a profit of 340,000 totals 4.6 million with no reserve. In a progress report the CEV was given as 2.75
A fixed price contract including a profit of 340,000 totals 4.6 million with no reserve. In a progress report the CEV was given as 2.75 million and actual cost was 2.8 million. What is the forecasted (estimated) profit in units of currency using forecasting based on the assumption that cost performance on the contract to date will continue for the remainder of the project?
Data on a project based on network calculation methods using planned duration and data on budgeted cost, actual duration, and actual cost for completed activities is below. Note that updated start and finish calculation is required for a portion of the question.
Activity | Predecessor | CPM Calculated Planned Start | Planned Duration | CPM Planned Finish | Activity Budget Cost | Actual Duration | Actual Cost |
A |
| 0 | 3 | 3 | 3,000 | 4 | 3,400 |
B | A | 3 | 4 | 7 | 8,400 | 5 | 9,600 |
C | B | 7 | 5 | 12 | 4,500 | 4 | 4,800 |
D | C | 12 | 6 | 18 | 6,600 |
|
|
E | D | 18 | 5 | 23 | 3,500 |
|
|
F | E | 23 | 4 | 27 | 3,600 |
|
|
G | F | 27 | 4 | 31 | 10,000 |
|
|
H | G | 31 | 2 | 33 | 1,800 |
|
|
a. What is the planned cumulative budgeted cost at the end of day 14?
b. Based on the actual finish times what is the actual cost at the end of day 14 including estimates of costs based on planned cost for activities in progress on that day assuming the project is executed on a soon as possible schedule?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started