A furniture maker is producing a dining chair. The following are the tasks to be performed and the duration of each task. Predecessors Duration (Days)
A furniture maker is producing a dining chair. The following are the tasks to be performed and the duration of each task. Predecessors Duration (Days) A Makin wooden les None B Making wooden seats None C Makin wooden backs D Cut cushions for seats E Cut cushions for backs F Make and attach cushion covers G Assemble dinin- chair 29000303 #m-hoaumoo ,E ,F Create an Activity-On-Node (AON) diagram based on the information provided