A Gantt chart shows a. The activities on the y-axis and the time on the x-axis. b. The time on y-axis and the activities on
A Gantt chart shows
a. The activities on the y-axis and the time on the x-axis.
b. The time on y-axis and the activities on x-axis.
c. The resources on y-axis and time on x-axis.
dThe dependencies between activities on y-axis and the time on x-axis.