A). Given the following information for a project, draw the AON (Activity-On-Node) project network. 1). Draw the AON (Activity-On-Node) project network. 2).What are the estimated
A). Given the following information for a project, draw the AON (Activity-On-Node) project network.
1). Draw the AON (Activity-On-Node) project network.
2).What are the estimated slack times (in weeks) for activities A-H?
3). What is the critical path.
Activity | Immediate Processor | Activity Time (days) |
A | - | 6 |
B | - | 8 |
C | A, B | 5 |
D | B | 4 |
E | C | 7 |
F | C, D | 3 |
G | D | 6 |
H | E, F, G | 5 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started