a) In order to determine the production quantities for the end items as specified by the MPS, two sources of information may be used. What are these? b) The weekly rated (calculated) capacity for a work center (WC) involving 3 machines is 140 standard hours. Each machine is available for 10 hours a day and 6 days a week. However, the WC was actually operated for 145 hours per week. Determine the efficiency of this WC. c) The following table lists the components needed to assemble an end item, the manufacturing or purchase lead times (in weeks)amount of on hand inventory, and the direct components (i.e. child items) of each item and the number of each component for each parent (in brackets). Item Lead time Amount on hand Direct components End item 1 1/2), C(I), K(3) L 2 10 B(2).J(3) C 3 15 G(2), B(2) K 3 20 H(4), B(2) B 2 30 J 30 G 3 5 H 2 0 0 1. If 40xnts of the end item are to be assembled, how many additional units of B are needed. WHITE CREW day and 6 days a week. However, the WC was actually operated for 145 hours per week. Determine the efficiency of this WC. e) The following table lists the components needed to assemble an end item, the manufacturing or purchase lead times (in weeks), amount of on hand inventory, and the direct components (ie, child items) of each item and the number of each component for each parent (in brackets) Item Lead time Amount on hand Direct components End item 1 0 LA2). C), K(3) 1 2 10 B(2). (3) 15 16(2), B(2) K 20 H(4), B(2) B 2 30 3 30 G 3 5 H 2 0 C 3 1. If 40 units of the end item are to be assembled, how many additional units of Bare needed 2. An order for 40 units of the end item is scheduled to be shipped at the start of week 8. What is the latest week that Luction or purchase of the components of the order can be started and the order would still be ready to ship on time? (Note: You do NOT need to develop the MRP record in onder to answer any of the questions in parte). a) In order to determine the production quantities for the end items as specified by the MPS, two sources of information may be used. What are these? b) The weekly rated (calculated) capacity for a work center (WC) involving 3 machines is 140 standard hours. Each machine is available for 10 hours a day and 6 days a week. However, the WC was actually operated for 145 hours per week. Determine the efficiency of this WC. c) The following table lists the components needed to assemble an end item, the manufacturing or purchase lead times (in weeks)amount of on hand inventory, and the direct components (i.e. child items) of each item and the number of each component for each parent (in brackets). Item Lead time Amount on hand Direct components End item 1 1/2), C(I), K(3) L 2 10 B(2).J(3) C 3 15 G(2), B(2) K 3 20 H(4), B(2) B 2 30 J 30 G 3 5 H 2 0 0 1. If 40xnts of the end item are to be assembled, how many additional units of B are needed. WHITE CREW day and 6 days a week. However, the WC was actually operated for 145 hours per week. Determine the efficiency of this WC. e) The following table lists the components needed to assemble an end item, the manufacturing or purchase lead times (in weeks), amount of on hand inventory, and the direct components (ie, child items) of each item and the number of each component for each parent (in brackets) Item Lead time Amount on hand Direct components End item 1 0 LA2). C), K(3) 1 2 10 B(2). (3) 15 16(2), B(2) K 20 H(4), B(2) B 2 30 3 30 G 3 5 H 2 0 C 3 1. If 40 units of the end item are to be assembled, how many additional units of Bare needed 2. An order for 40 units of the end item is scheduled to be shipped at the start of week 8. What is the latest week that Luction or purchase of the components of the order can be started and the order would still be ready to ship on time? (Note: You do NOT need to develop the MRP record in onder to answer any of the questions in parte)