Question

1 Approved Answer

A JIT / lean system uses kanban cards to authorize production and movement of materials. In one portion of the system, a work centre uses

A JIT/lean system uses kanban cards to authorize production and movement of materials. In one portion of the system, a work centre uses an average of 120 pieces of a part per hour. The manager has assigned a safety factor of 1.00. Standard containers are designed to hold six dozen pieces each. The cycle time for a kanban is 144 minutes.
How many kanbans are needed? (Round the final answer to the nearest whole number.)
Number of Kanbans

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Bears Of The World Ecology Conservation And Management

Authors: Vincenzo Penteriani, Mario Melletti

1st Edition

1108483526, 978-1108483520

More Books

Students also viewed these General Management questions

Question

5. If yes, then why?

Answered: 1 week ago

Question

6. How would you design your ideal position?

Answered: 1 week ago