A job was budgeted to require 2 hours of labor per unit at $11.00 per hour. The job consisted of 8,500 units and was completed
A job was budgeted to require 2 hours of labor per unit at $11.00 per hour. The job consisted of 8,500 units and was completed in 16,000 hours at a total labor cost of $189,100. What is the total labor cost variance?
-
$1,050 unfavorable.
-
$8,500 unfavorable.
-
$2,100 unfavorable.
-
$1,550 unfavorable.
-
$3,650 unfavorable.