A job was budgeted to require three hours of labor per unit at dollar 8 per hour. The job consisted of 8,000 units and was
A job was budgeted to require three hours of labor per unit at dollar 8 per hour. The job consisted of 8,000 units and was completed in 22,000 hours at a total labor cost of dollar 198,000. What is the total labor efficiency variance? dollar 22,000 unfavorable dollar 22,000 favorable dollar 6,000 unfavorable dollar 16,000 favorable dollar 16,000 unfavorable