A job was timed for 60 cycles and had an average of 1.12 minutes per piece. The
Fantastic news! We've Found the answer you've been seeking!
Question:
A job was timed for 60 cycles and had an average of 1.12 minutes per piece. The performance rating was 82%, and workday allowances are 7%. Determine each of the following:
a) Observed time (round answer to 2 decimals)
b) Normal Time (round answer to 2 decimals)
c) Standard Time (round answer to 2 decimals)