Question

1 Approved Answer

A labor crew for placing concrete consists of one labor foreman at $26.89 per hour, one cement finisher at $29.30 per hour, 3laborers at $24.45

A labor crew for placing concrete consists of one labor foreman at $26.89 per hour, one cement finisher at $29.30 per hour, 3laborers at $24.45 per hour each, and one equipment operator at $34.1 per hour. Such a crew, called a C20 crew, can place 156 cubic yards of concrete per 8-hour day.

Determine the cost per day of labor for the C20 crew.

The cost per day is determined to be ??? $ .

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Macroeconomics A European Perspective

Authors: Olivier Blanchard, Alessia Amighini, Francesco Giavazzi

4th Edition

1292360895, 9781292360898

More Books

Students also viewed these Economics questions

Question

What is cultural diversity?

Answered: 1 week ago

Question

Relax your shoulders

Answered: 1 week ago