A labor crew for placing concrete consists of one labor foreman at $26.89 per hour, one cement finisher at $29.30 per hour, 3laborers at $24.45
A labor crew for placing concrete consists of one labor foreman at $26.89 per hour, one cement finisher at $29.30 per hour, 3laborers at $24.45 per hour each, and one equipment operator at $34.1 per hour. Such a crew, called a C20 crew, can place 156 cubic yards of concrete per 8-hour day.
Determine the cost per day of labor for the C20 crew.
The cost per day is determined to be ??? $ .