A local government project that is currently being implemented has the following cost data as shown in the table below: ACTIVITY BUDGET %Planned Completion %
A local government project that is currently being implemented has the following cost data as shown in the table below:
ACTIVITY | BUDGET | %Planned Completion | % COMPLETION (Day 20) |
A | 60,000 | 30% | 25% |
B | 50,000 | 20% | 20% |
C | 200,000 | 100% | 80% |
D | 150,000 | 100% | 70% |
E | 45,000 | 70% | 50% |
F | 8,000 | 80% | 60% |
G | 22,000 | 50% | 40% |
Required
From the table above, kindly determine the following:
The earned value for the project
The planned value for the project
The schedule variance (SV)
The schedule performance index (SPI)
What can you conclude about the schedule performance of the project
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started