A local project being analysed by PERT has 42 activities, 13 of which are on the critical path. If the estmiated time along the

image text in transcribed

A local project being analysed by PERT has 42 activities, 13 of which are on the critical path. If the estmiated time along the critial path is 105 days with a project variance of 25, what is the probability that the project will be completed in 95 days or less? | Give your answer to 4 decimal places. I

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Managerial Approach

Authors: Jack R. Meredith, Samuel J. Mantel,

7th Edition

470226218, 978-0470226216

More Books

Students also viewed these Accounting questions

Question

Would another approach to the decision have worked better?

Answered: 1 week ago