A machine can produce 8 0 pieces in three hours but with five scraps. To produce 4 5 0 0 pieces with two machines: a

A machine can produce 80 pieces in three hours but with five scraps.
To produce 4500 pieces with two machines:
a. In one week (5 business days), how many hours a day should we run both machines?
Hint: First, find out how many pieces two machines can produce in one hour (productivity). Next, divide the total amount of work by this value to find out how many hours are required to complete the task. Finally, divide the total hours by 5 days to arrive at the answer.
b. If we work only 7.5 hours a day, how many business days should we run this machine?
Hint: You know the total time required from the question (a) above. Divide that value by daily working time to arrive at the answer.
c. Which option (a) or (b) do you prefer? Why?
d. If your customer requests the delivery in 8 days but the maximum daily operating time for a machine is limited to 10 hours, what alternative solutions can you suggest to your customer?
Hint: You can propose two alternatives: (1) Late delivery and (2) Less quantity in 8 days. You need to calculate the additional time you need and the total quantity you can produce in 8 days.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Transport Operations

Authors: Allen Stuart

2nd Edition

978-0470115398, 0470115394

More Books

Students also viewed these General Management questions

Question

How many stores exceeded the KPI target in 2015?

Answered: 1 week ago