Question
A manager must decide which type of machine to buy, A, B, or C. Machine costs (per individual machine) are as follows: Machine Cost A
A manager must decide which type of machine to buy, A, B, or C. Machine costs (per individual machine) are as follows: Machine Cost A $ 70,000 B $ 60,000 C $ 50,000
Product forecasts and processing times on the machines are as follows:
PROCCESSING TIME PER UNIT (minutes)
Product Annual
Demand A B C 1 11,000 5 1 2 2 24,000 5 6 2 3 26,000 2 4 5 4 22,000 1 6 3
a. Assume that only purchasing costs are being considered. Compute the total processing time required for each machine type to meet demand, how many of each machine type would be needed, and the resulting total purchasing cost for each machine type.The machines will operate 8 hours a day, 240 days a year.
Total processing time in minutes per machine: A B C
Number of each machine needed and total purchasing cost A $ B $ C $
b. Consider this additional information: The machines differ in terms of hourly operating costs: The A machines have an hourly operating cost of $13 each, B machines have an hourly operating cost of $11 each, and C machines have an hourly operating cost of $10 each.What would be the total cost associated with each machine option, including both the initial purchasing cost and the annual operating cost incurred to satisfy demand?
Total cost for each machine A B C
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started