A manual assembly line is being planned to produce a small consumer appliance. The work elements, element times, and precedence constraints are indicated in the
A manual assembly line is being planned to produce a small consumer appliance. The work elements, element times, and precedence constraints are indicated in the table below. The cycle time and repositioning time are 1 min and 0.2 min, respectively.
Work
element
To (min)
Immediate
1
2
2
4
3
1
4
3
5
5
6
6
7
8
predecessors
1
1
2
3
4,5,6
a) Construct the precedence diagram for this assembly line.
b) Determine total work content time (6 points)
c) Determine theoretical minimum number of workers required
d) Determine service time (6 points)
e) Determine repositioning efficiency (6 points)
f) Use the Largest Candidate Rule to solve the line balancing problem
Пе
Twc = Tek k=1
w* = Minimum Integer >
T
Tc
Ts=Tc-Tr
E=
Step by Step Solution
There are 3 Steps involved in it
Step: 1
a Precedence Diagram 1 2 3 2 3 4 1 4 5 6 5 6 7 8 b Total Work Content Time The total work content ti...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started