Question:
A manufacturing company is designing an assembly line to produce its main product. The line should be able to produce30units per hour. The following data in the Table give the necessary information.
Task | Immediate Predecessor | Task Time (sec) | ||
---|---|---|---|---|
A | None | 37 | ||
B | A | 50 | ||
C | A | 21 | ||
D | B | 40 | ||
E | C | 24 | ||
F | D, E | 58 | ||
G | F | 14 | ||
Which task is the bottleneck?
Taskselect a bottleneck task DFACEBG is the bottleneck.
Select the appropriate precedence diagram for the above information.
Compute the cycle time with a desired output of30units per hour.
C =enter cycle time in seconds per unit seconds/unit