A manufacturing plant is assessing its equipment performance. Requirements: Calculate the Overall Equipment Effectiveness (OEE) for a machine that operates 24 hours a day, 7
- A manufacturing plant is assessing its equipment performance.
- Requirements:
- Calculate the Overall Equipment Effectiveness (OEE) for a machine that operates 24 hours a day, 7 days a week. The machine's availability is 90%, performance efficiency is 80%, and quality rate is 95%.
- Propose actions to improve OEE.
- Explain how improving OEE supports Lean manufacturing principles.
Step by Step Solution
There are 3 Steps involved in it
Step: 1