Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

A manufacturing process has 12 workers and 6 stations. The process is completed in the order given below. Where there are multiple workers within a

A manufacturing process has 12 workers and 6 stations. The process is completed in the order given below. Where there are multiple workers within a station, each worker works independently on his/her own unit. Assume inventory buffers are allowed between each station.

Station

Staffing

Processing time/Activity time (hours/unit/worker)

A

2

2.20

B

1

1.25

C

3

2.00

D

2

2.60

E

3

3.00

F

1

0.75

What is the maximum number of units per hour that can be produced? Assume they start the day with inventory at each station to work on. (report your answer to 2 decimal places)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Linear Algebra and Its Applications

Authors: David C. Lay

4th edition

321791541, 978-0321388834, 978-0321791542

More Books

Students also viewed these Mathematics questions

Question

Evaluate 3x - 1 / x - 1. lim

Answered: 1 week ago