Question
1 Approved Answer
A maximum demand of generator station is 20MW , a load factor is 75% , a plant capacity factor is 50% and plant use factor
A maximum demand of generator station is 20MW , a load factor is 75% , a plant capacity factor is 50% and plant use factor of 80% .the reserve capacity of the plant in MW is: Select one: a. 50 b. 10 c