a Media 39 ourse Space Question 12 1 pts When comparing two independent projects, the correct decision would be to pick all projects with positive
a Media 39 ourse Space Question 12 1 pts When comparing two independent projects, the correct decision would be to pick all projects with positive NPVs. O pick only the project with the higher NPV, provided its NPV is positive. O pick only the project with the higher IRR. O pick only the protect with the higher NPV. O pick all projects with positive IRRs