A member of the proposal team is estimating the work activity duration using the Three-Point Estimating Method. The member has determined that the most likely
A member of the proposal team is estimating the work activity duration using the Three-Point Estimating Method. The member has determined that the most likely duration is 114 days, the pessimistic duration is 188 days, and the Optimistic duration is 90 days. Using the Beta Distribution Method, what is the Expected Activity Duration? Group of answer choices 245 Days 131 Days 122 Days 110 Days