A Metropolitan district is considering three alternative designs (D1, D2, D3) for a major water infrastructure project with a projected economic life of 15 years
A Metropolitan district is considering three alternative designs (D1, D2, D3) for a major water infrastructure project with a projected economic life of 15 years and interest rate of 8.5% per annum.
For each option, the Table below shows the construction cost (CT), annual maintenance and operating cost (MC) and annual net benefits (B) to the host and nearby communities. Given that the options are mutually exclusive, use cost-benefit analysis to establish which option should be built.
Confirm your answer using NPV scores.
Options | CT ( million) | MC ( million) | B ( million) |
D1 | 7.5 | 0.111 | 2.13 |
D2 | 8.4 | 0.125 | 2.45 |
D3 | 9.3 | 0.205 | 2.53 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started