Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

A mix of three materials into a process produces 0.9 litres of a finished product, with 10% loss of input in the process. Standard material

A mix of three materials into a process produces 0.9 litres of a finished product, with 10% loss of input in the process. Standard material costs are as follows per 0.9 litres of output. Material $ X 0.5 litres at $2 per litre 1.00 Y 0.4 litres at $1.50 per litre 0.60 Z 0.1 litres at $4 per litre 0.40 2.00 During a control period, 4,000 litres of output were produced. These used 2,810 litres of Material X; 1,910 litres of Material Y; and 380 litres of Material Z. What is the materials yield variance?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

To calculate the materials yield variance we need to determine the difference between the actual usage of materials and the standard expected usage ba... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Accounting

Authors: Stacey WhitecottonRobert LibbyRobert Libby, Patricia LibbyRobert Libby, Fred Phillips

1st Edition

0078110777, 9780078110771

More Books

Students also viewed these Accounting questions

Question

Explain the concept of shear force and bending moment in beams.

Answered: 1 week ago

Question

7. One or other combination of 16.

Answered: 1 week ago

Question

5. It is the needs of the individual that are important.

Answered: 1 week ago