A network consists of the activities in the following list. Times are given in weeks. Activity Preceding Time A -- 8 B -- 4 C

A network consists of the activities in the following list. Times are given in weeks.

Activity Preceding Time
A -- 8
B -- 4
C B 3
D A 3
E A, C 3
F D, E 4

(1) Please draw the project network diagram based on the table above.

(2) How many critical paths there are? What are they?

(3) What is project completion time?

(4) What is the slack time for activity E and activity C?

(5) If activity B is delayed by 1 weeks, will the project be delayed due to that? Why?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Marketing

Authors: Nigel Piercy and David Cravens

10th edition

78028906, 978-0078028908

More Books

Students also viewed these General Management questions

Question

List the numbers that are divisible by both 3 and 5.

Answered: 1 week ago

Question

Find the median for the set of measurements 2, 9, 11, 5, 6, 27.

Answered: 1 week ago

Question

Find the median for the set of measurements 2, 9, 11, 5, 6.

Answered: 1 week ago