A network consists of the activities in the following list. Times are given in weeks. Activity Preceding Time A -- 8 B -- 4 C
A network consists of the activities in the following list. Times are given in weeks.
Activity | Preceding | Time |
A | -- | 8 |
B | -- | 4 |
C | B | 3 |
D | A | 3 |
E | A, C | 3 |
F | D, E | 4 |
(1) Please draw the project network diagram based on the table above.
(2) How many critical paths there are? What are they?
(3) What is project completion time?
(4) What is the slack time for activity E and activity C?
(5) If activity B is delayed by 1 weeks, will the project be delayed due to that? Why?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started