A network consists of the following list. Times are given in weeks. Activity Preceding Optimistic Probable Pessimistic A -- 5 11 14 B - 3

A network consists of the following list. Times are given in weeks.

Activity

Preceding

Optimistic

Probable

Pessimistic

A

--

5

11

14

B

-

3

3

9

C

--

6

10

14

D

A, B

3

5

7

E

B

4

6

11

F

C

6

8

13

G

D, E

2

4

6

H

F

3

3

9

a. Draw the network diagram.

b. Calculate the expected duration and variance of each activity.

c. Calculate the expected duration and variance of the critical path.

d. Calculate the probability that the project will be completed in less than 28 weeks.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management

Authors: Jay Heizer, Barry Render

11th edition

9780132921145, 132921146, 978-0133408010

More Books

Students also viewed these General Management questions