A network consists of the following list. Times are given in weeks. Activity Preceding Optimistic Probable Pessimistic A -- 6 8 10 B - 3

A network consists of the following list. Times are given in weeks.

Activity Preceding Optimistic Probable Pessimistic
A -- 6 8 10
B - 3 9 15
C -- 6 8 10
D A, B 4 8 12
E B 4 6 8
F C 6 6 6
G D, E 2 6 10
H F 3 6 9

  1. Calculate the expected duration and variance of each activity.

Activity Preceding Opt. Prob. Pes. Expected Time Variance ES EF LS LF Slack CPVar
A -- 6 8 10
B - 3 9 15
C -- 6 8 10
D A, B 4 8 12
E B 4 6 8
F C 6 6 6
G D, E 2 6 10
H F 3 6 9
Total
Std. Dev.

2. Calculate the expected duration and variance of the critical path.

3. Calculate the probability that the project will be completed in less than 26 weeks.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Algebra and Trigonometry

Authors: Ron Larson

10th edition

9781337514255, 1337271179, 133751425X, 978-1337271172

More Books

Students also viewed these Mathematics questions

Question

Given A = r cos + r sin + 3z, find A at (2, 0, 3).

Answered: 1 week ago