A network consists of the following list. Times are given in weeks. Activity Preceding Optimistic Probable Pessimistic A -- 5 11 14 B - 3
A network consists of the following list. Times are given in weeks.
Activity | Preceding | Optimistic | Probable | Pessimistic |
A | -- | 5 | 11 | 14 |
B | - | 3 | 3 | 9 |
C | -- | 6 | 10 | 14 |
D | A, B | 3 | 5 | 7 |
E | B | 4 | 6 | 11 |
F | C | 6 | 8 | 13 |
G | D, E | 2 | 4 | 6 |
H | F | 3 | 3 | 9 |
a. Draw the network diagram.
b. Calculate the expected duration and variance of each activity.
c. Calculate the expected duration and variance of the critical path.
d. Calculate the probability that the project will be completed in less than 28 weeks.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started