Answered step by step
Verified Expert Solution
Question
1 Approved Answer
A new Civil Engineer failing to complete his contract worth 70000 pesos in a specified time is compelled to pay the penalty of 1/2 of
A new Civil Engineer failing to complete his contract worth 70000 pesos in a specified time is compelled to pay the penalty of 1/2 of 1%per day for the first 6 days of the extra time required, and for each additional day thereafter, the stipulated penalty is increased by 10% of 35.00 each day. If he pays a total penalty of 6160 pesos, by how many days did he overrun his contact time?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started