A new project manager is discussing risk management with his team. He's stressed that all known risks
Fantastic news! We've Found the answer you've been seeking!
Question:
A new project manager is discussing risk management with his team. He's stressed that all known risks must be accounted for and that all risks have to be avoided because they'll lead to project failure. What is wrong with his statement?
a. Only unknown risks lead to project failure b. Not all risks are to be avoided
c. Not all known risks have to be logged
d. Only unknown risks are to be avoided