A normal cost is incurred when: Select one: a . Additional temporary workers are brought on site. b . Overtime is used more than originally
A normal cost is incurred when:
Select one:
a
Additional temporary workers are brought on site.
b
Overtime is used more than originally planned.
c
Shipments are expedited.
d
The aggressive baseline plan is adhered to