A Overhead Variances Problem- The following information is for the third quarter of this year: Planned Actual Production 92,000 units 87,000 units Direct labor hours
A Overhead Variances Problem-
The following information is for the third quarter of this year:
Planned
Actual
Production
92,000
units
87,000
units
Direct labor hours
506,800
DL hrs
380,000
DL hrs
Fixed manufacturing overhead
$205,000
$182,400
Variable manufacturing overhead
$910,000
$841,500
Standard direct labor hour per unit
5.5
REQUIRED:
Calculate the following three overhead variances:
1. Overhead volume variance
2. Overhead efficiency variance
3. Overhead spending variance
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started