Question: A partially solved PERT problem is detailed in the table below. Times are given in weeks. table [ [ Activity , Preceding,Optimistic,Probable,Pessimistic,Expected,Variance ] ,

A partially solved PERT problem is detailed in the table below. Times are given in weeks.
\table[[Activity,Preceding,Optimistic,Probable,Pessimistic,Expected,Variance],[,,Time,Time,Time,Time,],[A,-,7,9,14,,],[B,A,2,2,8,,],[C,A,8,12,16,,],[D,-,3,5,10,,],[E,C,4,6,8,,],[F,B,6,8,10,,],[G,F,2,3,4,,],[H,D, E,2,2,8,,],[1,G,6,8,16,,]]
 A partially solved PERT problem is detailed in the table below.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To solve this PERT Program Evaluation and Review Technique problem well calculate the expected time ... View full answer