a permit is obtained on friday aug 1, the material are to be delivered aug 8 the material are needed labor begins on aug 11
a permit is obtained on friday aug 1, the material are to be delivered aug 8
the material are needed labor begins on aug 11
it is estimated 15 days of labor are required
the crew will work everyday including weekends and holidays
the project is scheduled to be completed on sep 8.
how many floating days are available for this project?