Question

1 Approved Answer

a permit is obtained on friday aug 1, the material are to be delivered aug 8 the material are needed labor begins on aug 11

a permit is obtained on friday aug 1, the material are to be delivered aug 8
the material are needed labor begins on aug 11
it is estimated 15 days of labor are required
the crew will work everyday including weekends and holidays
the project is scheduled to be completed on sep 8.
how many floating days are available for this project?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting And Reporting

Authors: Mr Barry Elliott, Jamie Elliott

16th Edition

027377817X, 978-0273778172

More Books

Students also viewed these Accounting questions