Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

A PERT project has 45 activities, 19 of which are on the critical path. The estimated time for the critical path is 120 days. The

A PERT project has 45 activities, 19 of which are on the critical path. The estimated time for the critical path is 120 days. The sum of all activity variances is 64, while the sum of variances along the critical path is 36. What is the probability that the project can be completed between days 108 and 120% Select one: O a. 0.4773 O b. 0.1058 c. 0.9773 O d. 0.0227 e. 2.00image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Construction Accounting And Financial Management

Authors: Steven J. Peterson

4th Edition

0135232872, 978-0135232873

More Books

Students also viewed these Accounting questions

Question

Excel caculation on cascade mental health clinic

Answered: 1 week ago