A PERT project is detailed in the table below. Durations are given in days.

Activity Predecessors Optimistic duration Pessimistic duration Most likely duration Expectation Variance
A - 23 29 27
B A 46 58 54
C A 22 28 26
D A 30 42 38
E B 23 29 27
F B, C 21 27 25
G C, F 45 63 57
H G 23 29 27
I F, H 28 34 32
J E, I 33 39 37
K F, H, I 24 30 28
  1. Draw an activity-on-node network representing this project.
  2. Give the expected duration and variance of each activity in the table.
  3. What is the expected duration of the project?
  4. What is the variance in the project's duration?
  5. How many days are needed for the project to be 80% likely to be completed?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project management

Authors: Harvey maylor

4th Edition

027370432X, 978-0273704324

More Books

Students also viewed these General Management questions

Question

Respond to the questions in Consumer Insight 32.

Answered: 1 week ago

Question

define job satisfaction and job performance;

Answered: 1 week ago

Question

Differentiate sin(5x+2)

Answered: 1 week ago

Question

Compute the derivative f(x)=1/ax+bx

Answered: 1 week ago

Question

What is job enlargement ?

Answered: 1 week ago

Question

A. Why do you think Bezos bans PowerPoint slides in meetings?

Answered: 1 week ago

Question

G. Explain various approaches for reviewing reports.

Answered: 1 week ago