A PERT project is detailed in the table below. Durations are given in days. Activity Predecessors Optimistic duration Pessimistic duration Most likely duration Expectation Variance

A PERT project is detailed in the table below. Durations are given in days.

Activity Predecessors Optimistic duration Pessimistic duration Most likely duration Expectation Variance
A - 23 29 27
B A 46 58 54
C A 22 28 26
D A 30 42 38
E B 23 29 27
F B, C 21 27 25
G C, F 45 63 57
H G 23 29 27
I F, H 28 34 32
J E, I 33 39 37
K F, H, I 24 30 28
  1. Draw an activity-on-node network representing this project.
  2. Give the expected duration and variance of each activity in the table.
  3. What is the expected duration of the project?
  4. What is the variance in the project's duration?
  5. How many days are needed for the project to be 80% likely to be completed?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Exploring The Hospitality Industry

Authors: John R Walker

4th Edition

0134744934, 9780134744933

More Books

Students also viewed these General Management questions

Question

5. Give some examples of hidden knowledge.

Answered: 1 week ago