A plan that identifies the allocated resources, the project's goals, and the schedule that allows an organization to achieve those goals is: The work breakdown
A plan that identifies the allocated resources, the project's goals, and the schedule that allows an organization to achieve those goals is:
The work breakdown structure.
The project budget.
The statement of work.
The risk management plan.