Question
A Power Plant needs to replace an ageing Boiler with a badly degraded efficiency, resulting in an excessive consumption of fuel; the Power Plant is
A Power Plant needs to replace an ageing Boiler with a badly degraded efficiency, resulting in an excessive consumption of fuel; the Power Plant is expected to keep producing electric power for an indefinite period.
Plant Management issues a Request For Proposal to purchase a new Boiler, specifying the required efficiency. Three proposals are received from three competing manufacturers:
- Proposal A offers a Stainless-Steel tubing boiler with a useful life of 40 years and needing a major refurbishing every 20 years.
- Proposal B offers a Copper tubing boiler with a useful life of 30 years and needing a major refurbishing every 10 years.
- Proposal C offers a Titanium tubing boiler with a useful life of 50 years and no major refurbishing needed.
Proposals data are as follows:
Proposal A Proposal B Proposal C
Price ($) 500,000 350,000 600,000
Maintenance ($/yr) 50,000 70,000 20,000
Refurbishing ($) 60,000 50,000 0
Refurbishing interval (yr) 20 10 N/A
Fuel savings ($/yr) 30,000 30,000 30,000
Boiler useful Life (yr) 40 30 50
Salvage Value ($) 100,000 70,000 150,000
Plant Management evaluates the proposals using the following parameters and criteria:
- Yearly worth of money availability: i= 2.75%
- Assume equal replacements
- No refurbishing to be implemented at end of useful life
- Maintenance to continue including last year of useful life
- Maximize estimated annual net worth of boiler operation
Question: Which Proposal will Plant Management select?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started