Question

1 Approved Answer

A Predecessors Optimistic time Most Likely time Pessimistic time 4 5 8 B A n 5 7 10 C A 3 5 9 D

image text in transcribed

A Predecessors Optimistic time Most Likely time Pessimistic time 4 5 8 B A n 5 7 10 C A 3 5 9 D A 2 7 9 E B 7 9 15 EL F C 8 11 16 G D 6 8 11 H F.G 7 12 16 I E 6 9 12 J H,I 3 7 10 K J 3 11 a. Draw the Network Diagram? (5 Points) b. Find the Critical Variance? (2 Points) C. What is the Project Duration? (2 Points) d. What is the Project Critical Path? (2 Points) e. What is the Probability of Project completion in 48 weeks? (2 Points) f. 20 With a Probability of 99%, how long the project will take? (2 Points) a ht

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Business Analysis Valuation Using Financial Statements

Authors: Paul M. Healy

5th edition

1111972303, 978-1111972301

More Books

Students also viewed these Accounting questions

Question

A call feature a. allows bondholders to corvert their

Answered: 1 week ago