Question

1 Approved Answer

A . Prepare Site 5 days None B . Install Rough Plumbing 4 days Prepare Site C . Pour Concrete Foundation 4 days Install Rough

A. Prepare Site 5 days None
B. Install Rough Plumbing 4 days Prepare Site
C. Pour Concrete Foundation 4 days Install Rough Plumbing
D. Concrete Curing Time 3 days Pour Concrete Foundation
E. Preassemble Wall Frames 10 days None
F. Erect Wall Frames 5 days Preassemble Wall Frames, Cure Concrete
G. Install Roof 2 days Erect Wall Frames
H. Install Wiring 5 days Install Roof
I. Install Exterior Siding 4 days Install Roof
J. Install Insulation 2 days Install Exterior Siding
K. Hang Drywall 4 days Install Insulation, Install Wiring
L. Install Windows 1 day Hang Dry Wall
M. Paint Interior 8 days Install Windows
N. Paint Exterior 4 days Install Exterior Siding
O. Level Yard 3 days Cure Concrete
P. Landscape Yard 4 days Level Yard
Click here for the Excel Data File
a-1. Calculate the earliest start and finish for each task.
a-2. Calculate the slack for every project activity.
a-3. Identify the critical path.
c-1. What will happen to the project if the materials needed for the frame preassembly are not available until the second day of the project?
c-2. What if the materials were delayed until the tenth day?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Transport Operations

Authors: Allen Stuart

2nd Edition

978-0470115398, 0470115394

More Books

Students also viewed these General Management questions