A . Prepare Site 5 days None B . Install Rough Plumbing 4 days Prepare Site C . Pour Concrete Foundation 4 days Install Rough
A Prepare Site days None
B Install Rough Plumbing days Prepare Site
C Pour Concrete Foundation days Install Rough Plumbing
D Concrete Curing Time days Pour Concrete Foundation
E Preassemble Wall Frames days None
F Erect Wall Frames days Preassemble Wall Frames, Cure Concrete
G Install Roof days Erect Wall Frames
H Install Wiring days Install Roof
I. Install Exterior Siding days Install Roof
J Install Insulation days Install Exterior Siding
K Hang Drywall days Install Insulation, Install Wiring
L Install Windows day Hang Dry Wall
M Paint Interior days Install Windows
N Paint Exterior days Install Exterior Siding
O Level Yard days Cure Concrete
P Landscape Yard days Level Yard
Click here for the Excel Data File
a Calculate the earliest start and finish for each task.
a Calculate the slack for every project activity.
a Identify the critical path.
c What will happen to the project if the materials needed for the frame preassembly are not available until the second day of the project?
c What if the materials were delayed until the tenth day?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started