Question
A private school is considering the purchase of six school buses to transport students to and from school events. The initial cost of the buses
A private school is considering the purchase of six school buses to transport students to and from school events. The initial cost of the buses is $600,000. The life of each bus is estimated to be five years, after which time the vehicles would have to be scrapped with no salvage value. The school’s management team has derived the following estimates for annual revenues and cost for the next five years.
| Year 1 | Year 2 | Year 3 | Year 4 | Year 5 |
Revenues | $330,000 | $330,000 | $350,000 | $380,000 | $400,000 |
Driver costs | $33,000 | $35,000 | $36,000 | $38,000 | $40,000 |
Repairs & maintenance | $8,000 | $13,000 | $15,000 | $16,000 | $18,000 |
Other costs | $130,000 | $135,000 | $140,000 | $136,000 | $142,000 |
Annual depreciation | $120,000 | $120,000 | $120,000 | $120,000 | $120,000
|
The buses would be purchased at the beginning of the project (i.e., in Year 0) and all revenues and expenditures shown in the table above would be incurred at the end of each relevant year.
Because schools are exempt from taxes, the school’s corporate tax rate is 0 percent. A business consultant has advised management that they should use a weighted average cost of capital (WACC) of 10.5 percent to evaluate this project.
Prepare a table showing the estimated net cash flows for each year of the project. Explain all steps involved in your calculation of the Year 1 estimated net cash flow.
Calculate the project’s Payback Period. Explain in your own words, all steps involved in the calculation process.
Calculate the project’s Internal Rate of Return (IRR). Explain in your own words, all steps involved in the calculation process.
Calculate the project’s Net Present Value (NPV). Explain in your own words, all steps involved in the calculation process.
Which is the three evaluation techniques that you computed (i.e., payback period, IRR and NPV), should the firm use to make its decision of whether or not to accept this project? Why? Is one of these techniques better than the others and if so, why?
Finally, what are some risk factors inherent in this capital budgeting analysis? That is, make a list of at least three items that could cause the outcome of this project to be substantially worse than management currently expects (as reflected in their revenue and cost estimates, WACC estimate, etc.). Fully explain each of the risk factors you identify.
Step by Step Solution
3.54 Rating (164 Votes )
There are 3 Steps involved in it
Step: 1
Income revenue driver cost repairs other cost depreciation net cash flow income depreciation depreci...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started