Question
1 Approved Answer
A process that is considered to be in control measures an ingredient in ounces. Below are the last 10 samples (each of size n =
A process that is considered to be in control measures an ingredient in ounces. Below are the last 10 samples (each of size n = 5) taken. The population standard deviation is 1.36.
SAMPLES
1 2 3 4 5 6 7 8 9 10
10 9 13 10 12 10 10 13 8 10
9 9 9 10 10 10 11 10 8 12
10 11 10 11 9 8 10 8 12 9
9 11 10 10 11 12 8 10 12 8
12 10 9 10 10 9 9 8 9 12
a) What is the process standard deviation ?
b) If z = 3, what are the control limits for the mean chart?
c) What are the control limits for the range chart?
d) Is the process in control?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started