Question

1 Approved Answer

A product has annual demand of 1 0 0 , 0 0 0 units. The plant manager wants production to follow a four - hour

A product has annual demand of 100,000 units. The plant manager wants production to follow a four-hour cycle. Based on the following data, what setup time will enable the desired production cycle?
d =400 per day (250 days per year), p =
2,500
units per day, H =
$120
per unit per year, Q =200(demand for four hours, half a day), and the hourly labor rate is $18.(Do not round intermediate calculations. Round final answer to one decimal place.)
A.71.2
B.67.2
C.134.4
D.6.0
E.20.2

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management And The Arts

Authors: William J. Byrnes

6th Edition

0367258900, 978-0367258900

More Books

Students also viewed these General Management questions

Question

What are the core functions of the universitys HRM department?

Answered: 1 week ago

Question

Identify a set of competencies for tenured faculty

Answered: 1 week ago