A product has annual demand of 100,000 units. The plant manager wants production to follow a four-hour cycle. Based on the following data, what
A product has annual demand of 100,000 units. The plant manager wants production to follow a four-hour cycle. Based on the following data, what setup cost will enable the desired production cycle? d=400 per day (250 days per year), p=4000 units per day, H=$40 per unit per year, and Q=200 (demand for four hours, half a day). $18.00 $2.00 $1,036.80 $64.00 $7.20