Question

1 Approved Answer

A production line has three machines A, B, and C, with reliabilities of .99, .96, and .93, respectively. The machines are arranged so that if

A production line has three machines A, B, and C, with reliabilities of .99, .96, and .93, respectively. The machines are arranged so that if one breaks down, the others must shut down. Engineers are weighing two alternative designs for increasing the lines reliability. Plan 1 involves adding an identical backup line, and plan 2 involves providing a backup for each machine. In either case, three machines (A, B, and C) would be used with reliabilities equal to the original three.
a. Which plan will provide the higher reliability?
b. Explain why the two reliabilities are not the same.
c. What other factors might enter into the decision of which plan to adopt?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Next Step Advanced Medical Coding And Auditing

Authors: Carol J. Buck

1st Edition

0323430775, 978-0323430777

More Books

Students also viewed these Accounting questions

Question

Why would Baer do this if he didnt expect to get paid?

Answered: 1 week ago

Question

LO6 Define harassment and the role that HR plays in addressing it.

Answered: 1 week ago