A production manager needs to develop a production schedule to meet the following demand: Period 1 2 3 4 5 6 Demand 600 600 800

A production manager needs to develop a production schedule to meet the following demand:

Period 1 2 3 4 5 6
Demand 600 600 800 1000 1200 600

Productions costs are as follows: (a) regular time: $3 per unit. (b) over-time: $5 per unit. (c) subcontract: $7 per unit. (d) Inventory carrying cost = $2 per unit per period (e) Back-order costs = $5 per unit per period.

Suppose some workers have retired, and the regular production rate can be only 700 units per period. Further, no subcontracting is allowed. However, it is possible to schedule production on an over-time basis .

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Finance And Accounting For Nonfinancial Managers

Authors: Steven A. Finkler

5th Edition

9780808046905

More Books

Students also viewed these Accounting questions